Question: Where will the following projects plot in relation to the security market line if the risk-free rate is 6% and the market risk premium is
Where will the following projects plot in relation to the security market line if the risk-free rate is 6% and the market risk premium is 9%? Which projects should be undertaken
| Project | Beta | IRR |
| A | 2.0 | 25% |
| B | 1.6 | 22% |
| C | 1.1 | 15% |
| D | 0.8 | 11% |