Question: Which activity should be treated as a project? Select one: a. Implementing a new computerized maintenance management system (CMMS). b. Setting schedules for the security

  1. Which activity should be treated as a project?

Select one:

a. Implementing a new computerized maintenance management system (CMMS).

b. Setting schedules for the security staff.

c. Regularly scheduled preventive maintenance on an air conditioner.

d. Weekly inspections of safety equipment.

  1. Facility management projects are typically used to accomplish which of the following?

Select one:

a. Implement a new organizational structure, staffing or systems.

b. Respond to a merger/acquisition, rapid growth, or downsizing.

c. Implementation of all operations and maintenance activities.

d. Respond to a project sponsors mandate for a capital project even if release of capital funds is denied.

  1. Which activity unifies the independent project components?

Select one:

a. Scoping and communications

b. Use of the Plan, Do, Check, Act model

c. Integration or coordination

d. Use of project scheduling tools

  1. A facility manager is determining whether he should be the project manager on a project. Which of the following is true of this decision?

Select one:

a. The facility manager can manage a more complex project if he has frequently managed similar projects.

b. The facility manager is never the project manager for projects.

c. Except for major construction, facility managers are the project manager for all facility projects.

d. If a project is within the facility managers capabilities, there is no reason why he could not manage it.

  1. Which of the following is true of project models?

Select one:

a. Phases in project models should not be altered.

b. Traditional waterfall models incorporate planned iteration.

c. The Plan, Do, Check, Act model has a finite duration.

d. Planned iteration allows omission of some details to be added later.

  1. What can project models be applied to?

Select one:

a. The project as a whole but not to individual processes or phases.

b. Individual processes and phases or to the project as a whole.

c. The project as a whole or to individual processes, but not phases.

d. Individual process and phases but not the project as a whole.

  1. Which of the following statements regarding the PMBOK process groups is false?

Select one:

a. The PMBOK process groups is a method for categorizing key project tasks.

b. There is no overlapping between the PMBOK process groups, as no tasks can be performed iteratively.

c. Every process within a project activity fits into at least one of the PMBOK process groups.

d. PMBOK recognizes five project management process groups.

  1. What should you check to confirm a project is directly linked to the organization's long term plan?

Select one:

a. Strategic facility plan

b. Project objectives statement

c. Success criteria

d. Project charter

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!