Question: Which activity should be treated as a project? Setting schedules for the security staff. Scheduling preventive maintenance on an air conditioner. Implementing a new computerized

Which activity should be treated as a project?
Setting schedules for the security staff.
Scheduling preventive maintenance on an air conditioner.
Implementing a new computerized maintenance management system (CMMS).
Conducting inspections of safety equipment.