Question: Which are required to create the schedule management plan? Enterprise environmental factors, organizational process assets, project charter, and project management plan Scope baseline, work breakdown

Which are required to create the schedule management plan?
Enterprise environmental factors, organizational process assets, project charter, and project management plan
Scope baseline, work breakdown structure (WBS), estimated costs, and milestone list
Activity list, project statement of work, project charter, and communications management plan
Resource management plan, organizational process assets, activity list, and business case