Which best describes the difference between general and joboverhead costs? General overhead costs that are incurred regardless
Question:
Which best describes the difference between general and joboverhead costs?
General overhead costs that are incurred regardless of whether aproject is being executed. These are the costs associated withoperating the construction company. Conversely, job overhead is theadministrative costs directly associated with the execution of aspecific project | ||
General overhead costs that are incurred after a project isbeing executed, job overhead is the administrative costs directlyassociated with the execution of a specific project. These are thecosts associated with operating the construction company | ||
General overhead costs that are incurred regardless of whether aproject is being executed. These are the costs associated withoperating the owner new facility. Conversely, job overhead is theadministrative costs directly associated with the execution of aspecific project | ||
None of these |