Question: Which diagramming method below only allows for the use of the Finish - Start dependency? The activity diagramming method The arrow diagramming method The precedence
Which diagramming method below only allows for the use of the Finish Start dependency?
The activity diagramming method
The arrow diagramming method
The precedence diagramming method
The activity on node method