Question: Which diagramming method below only allows for the use of the Finish - Start dependency? The activity diagramming method The arrow diagramming method The precedence

Which diagramming method below only allows for the use of the Finish - Start dependency?
The activity diagramming method
The arrow diagramming method
The precedence diagramming method
The activity on node method