Question: Which is correct for complex user stories? Instruction: Choose all options that best answer the question. Progress cannot be measured because the work is too
Which is correct for complex user stories? Instruction: Choose all options that best answer the question. Progress cannot be measured because the work is too large They are known as epics and they should be split They cannot be split and must be performed over more than one sprint Progress can be measured by setting small milestones