Question: Which is incorrect about MRP records? a. MRP processing takes the BOM, MPS, and Inventory Records as inputs b. Planned Order Releases are Planned Order
Which is incorrect about MRP records?
a. MRP processing takes the BOM, MPS, and Inventory Records as inputs
b. Planned Order Releases are Planned Order Receipts offset by lead time
c. Planned Order Receipts and Net Requirements of an item may differ depending on the lot-sizing rule
d.The Gross Requirements for a parent item are calculated from the Planned Order Releases of the child item(s)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts