Question: Which is NOT a reason to save additional baselines in a project? to record significant changes to the project without losing original baseline values to

Which is NOT a reason to save additional baselines in a project?
to record significant changes to the project without losing original baseline values
to save a baseline that includes changes due to approved change requests
to change the original baseline to obtain management approval
to track performance trends over time