Question: Which is NOT an option for reducing the critical path? Group of answer choices Overlap sequential tasks Lengthen early tasks Eliminate tasks on the critical
Which is NOT an option for reducing the critical path?
Group of answer choices
Overlap sequential tasks
Lengthen early tasks
Eliminate tasks on the critical path
Shorten easiest tasks