Question: Which is NOT correct about Critical Path in the activity network of a project ? Activities on the Critical Path have zero float. Activities on
Which is NOT correct about Critical Path in the activity network of a project Activities on the Critical Path have zero float. Activities on the Critical Path is used to estimate the total project cost It is the sequence of activities that represents the longest path through a project among multiple possible paths. determines the shortest possible duration of the project