Question: Which statement is FALSE? Group of answer choices There may be multiple critical paths. The length of the critical path determines the project completion time.
Which statement is FALSE?
Group of answer choices
There may be multiple critical paths.
The length of the critical path determines the project completion time.
Critical path activities must have zero slack.
Delaying an activity on a critical path does not delay the project.
Crashing noncritical path activities has no impact on the project completion time.