Question: Which is not one of the basic rules to follow when developing project networks? a . An activity identification number must be larger than that
Which is not one of the basic rules to follow when developing project networks?
a
An activity identification number must be larger than that of any preceding activities.
b
Conditional statements are allowed but looping statements are not allowed.
c
Each activity must have a unique identification number.
d
An activity cannot begin until all preceding activities have been completed.