Question: Which is not one of the basic rules to follow when developing project networks? a . An activity identification number must be larger than that

Which is not one of the basic rules to follow when developing project networks?
a.
An activity identification number must be larger than that of any preceding activities.
b.
Conditional statements are allowed but looping statements are not allowed.
c.
Each activity must have a unique identification number.
d.
An activity cannot begin until all preceding activities have been completed.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock