Question: Which is not true about the PERT schedule? Select the most appropriate one. a . The project duration is 9 . b . Activity B
Which is not true about the PERT schedule? Select the most appropriate one.
a The project duration is
b Activity B has the longest expected duration among the four activities.
c The standard deviation for Activity Cs duration is
d There is only one critical path.Figure