Question: Which is not true about the PERT schedule? Select the most appropriate one. a . The project duration is 9 . b . Activity B

Which is not true about the PERT schedule? Select the most appropriate one.
a. The project duration is 9.
b. Activity B has the longest expected duration among the four activities.
c. The standard deviation for Activity Cs duration is 1/3.
d. There is only one critical path.Figure 4