Question: Which is the most comprehensive solution for a firm if a load report shows not enough capacity is available? a . Find more capacity b

Which is the most comprehensive solution for a firm if a load report shows not enough capacity is available?
a. Find more capacity
b. Change the master production schedule
c. Change both the master production schedule and add capacity
d. Rerun MRP