Question: Which item represents the inputs to the Plan Communications Management process? (LO-10) Group of answer choices The project management plan, team charter, and the stakeholder

Which item represents the inputs to the Plan Communications Management process? (LO-10) Group of answer choices The project management plan, team charter, and the stakeholder register Enterprise environmental factors, the project management plan, and team charter Enterprise environment factors, organizational process assets, and issue log Organizational process assets, the project management plan, and the stakeholder register