Question: Which knowledge area includes processes required to identify, define, and control what is included and excluded in the project?a . Project Scope Managementb. Project Risk

Which knowledge area includes processes required to identify, define, and control what is included and excluded in the project?a. Project Scope Managementb. Project Risk Managementc. Project Stakeholder Managementd. Project Integration Management
 Which knowledge area includes processes required to identify, define, and control