Question: Which of the following statement is FALSE? A. Process time is the only value-added activity in the four components of throughput time. B. Throughput time
Which of the following statement is FALSE? A. Process time is the only value-added activity in the four components of throughput time. B. Throughput time is the elapsed time from when a customer order is received to when the completed order is shipped. C. Throughput time is a nonfinancial performance measure. D. A companys manufacturing cycle efficiency can be improved by minimizing queue time.