Which of the following statements regarding PERT analysis is NOTtrue? Project standard deviation is the sum of
Fantastic news! We've Found the answer you've been seeking!
Question:
Which of the following statements regarding PERT analysis is NOTtrue?
Project standard deviation is the sum of all critical activitystandard deviations.
Each activity has three estimates of its duration.
Only critical activities contribute to the project variance.
The most likely time is different from the expected activitytime.
Project variance is the sum of all critical activityvariances.