Question: Which of the Project Time management processes involves identifying and documenting dependencies among schedule activities? Group of answer choices Define activities Control schedule Sequence activities
Which of the Project Time management processes involves identifying and documenting dependencies among schedule activities?
Group of answer choices
Define activities
Control schedule
Sequence activities
Develop schedule