Question: which of the statement concuring project risk is false? a.the larger the project size,the more likely the project will fail. b.the more structured a project
which of the statement concuring project risk is false?
a.the larger the project size,the more likely the project will fail.
b.the more structured a project is,the less likely the project will fail.
c.the more experience there is with technology in the team ,the less likely the project will fail.
d.the younger the project manager is,more likely the project will fail.