Question: Which on eof the following will decrease the net present value of a project a. a decrease in the initial capital requirement b. an increase
Which on eof the following will decrease the net present value of a project
a. a decrease in the initial capital requirement
b. an increase in the required rate of reture
c. an increase in the initial capital requirement
d. a deferment of some cash inflows until a later year
e. a reduction in the final cash flow