Question: Which one is INCORRECT about project scheduling? a) It is normal for activities on the critical path to be delayed without delaying the entire project.

Which one is INCORRECT about project scheduling?
Which one is INCORRECT about project scheduling? a) It is normal for activities on the critical path to be delayed without delaying the entire project. b) A key distinction of the critical path is that all activities on the critical path have zero slack time. c) The length of time an activity can be delayed without affecting the project completion time is the slack. d) A critical activity can be part of a noncritical path