Question: Which one is not correct about contingency reserve? It is the budget allocated for identified risks. The sum of contingency reserve and cost baseline is

Which one is not correct about contingency reserve? It is the budget allocated for identified risks. The sum of contingency reserve and cost baseline is the project budget The sum of contingency reserve and work package cost estimates is the cost baseline of a project. is also called contingency allowance.