Question: Which output from the Plan Scope Management process identifies the change control process used for requirements? Group of answer choices Requirements documentation Requirements traceability matrix
Which output from the Plan Scope Management process identifies the change control process used for requirements? Group of answer choices
Requirements documentation
Requirements traceability matrix
Project management plan
Requirements management plan