Question: Which process involves working with stakeholders to create the document that formally authorizes a project? a . Developing the preliminary project scope statement b .

Which process involves working with stakeholders to create the document that formally authorizes a project?
a.
Developing the preliminary project scope statement
b.
Developing the project management plan
c.
Performing integrated change control
d.
Developing the project charter