Question: Which project lite cycle phase includes the development of time estimates for the completion of activities? o Execution o Planning o Conception o Feasibility analysis
Which project lite cycle phase includes the development of time estimates for the completion of activities?
o Execution
o Planning
o Conception
o Feasibility analysis