Question: Which risk management processes use the risk register and the risk report A. They are used by all the risk management processes throughout the project.

Which risk management processes use the risk register and the risk report A. They are used by all the risk management processes throughout the project. B. The risk register is used during risk identification, and the risk report is used during risk monitoring. C. The risk register is used during risk identification and risk response planning. The risk report is used during risk response implementation and risk monitoring. D. They are both used during risk identification and risk monitoring