Question: Which risk management processes use the risk register and the risk report? The risk register is used during risk identification and risk response planning. The
Which risk management processes use the risk register and the risk report?
The risk register is used during risk identification and risk response planning. The risk report is used during risk response implementation and risk monitoring.
They are used by all the risk management processes throughout the project.
They are both used during risk identification and risk monitoring.
The risk register is used during risk identification, and the risk report is used during risk monitoring.