Question: Which schedule compression method used for project recovery utilizes resources already assigned to the project and redeploys them to the critical path in the same

Which schedule compression method used for project recovery utilizes resources already assigned to the project and redeploys them to the critical path in the same time oeriod?
A. Resource Crashing
B. Fast tracking
C. Slack management
D. Resource substitution