Question: Which schedule compression technique allows activities to overlap? A . Effort driven. B . Fast - tracking. C . Buffering. D . Crashing. E .
Which schedule compression technique allows activities to overlap?
A Effort driven.
B Fasttracking.
C Buffering.
D Crashing.
E Coupling.