Question: Which sequence is best? a)First prepare the activity network, then the work breakdown structure, then the resource-loading form b)First prepare the work breakdown structure, then
Which sequence is best?
a)First prepare the activity network, then the work breakdown structure, then the resource-loading form
b)First prepare the work breakdown structure, then the activity network, then the resource-loading form
c)First prepare the resource-loading form, then the work breakdown structure, then the activity network
d)First prepare the resource-loading form, then the activity network, then the work breakdown structure
The highest element in the breakdown of the WBS is:
a)A work package
b)Sub-deliverables
c)A cost account
d)Major deliverables
e)The project