Question: Which sequence is best? a)First prepare the activity network, then the work breakdown structure, then the resource-loading form b)First prepare the work breakdown structure, then

Which sequence is best?

a)First prepare the activity network, then the work breakdown structure, then the resource-loading form

b)First prepare the work breakdown structure, then the activity network, then the resource-loading form

c)First prepare the resource-loading form, then the work breakdown structure, then the activity network

d)First prepare the resource-loading form, then the activity network, then the work breakdown structure

The highest element in the breakdown of the WBS is:

a)A work package

b)Sub-deliverables

c)A cost account

d)Major deliverables

e)The project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!