Question: Which statement is correct? Group of answer choices The weekly plan should be defined by the external client only Milestones should be elicited in the
Which statement is correct?
Group of answer choices
The weekly plan should be defined by the external client only
Milestones should be elicited in the lookahead plan
Concrete pour is a welldefined task for a weekly plan.
Gantt charts show the location in which construction activities take place similarly to the LineofBalance LOB diagrams.
A plan is a forecast and as such has some level of uncertainty