Question: Which statement is correct? Group of answer choices A plan is a forecast and as such has some level of uncertainty Concrete pour is a
Which statement is correct?
Group of answer choices
A plan is a forecast and as such has some level of uncertainty
Concrete pour is a welldefined task for a weekly plan.
Milestones should be elicited in the lookahead plan
Gantt charts show the location in which construction activities take place similarly to the LineofBalance LOB diagrams.
The weekly plan should be defined by the external client only