Question: Which statement is correct? ( week 5 ) Group of answer choices Left to right check of the schedule is used during the weekly planning

Which statement is correct? (week 5)
Group of answer choices
"Left to right" check of the schedule is used during the weekly planning sessions
The removal of constrains is monitored during the long term planning
Milestones should be defined in the look ahead planning
If a task is not fully completed, the NO column can be checked for this task on the weekly plan
Reasons for non-completion for weekly tasks should be identified on phase pull planning session