Question: Which statement is not correct regarding the backward pass calculations and its algorithm? a .The late start timing is passed to the preceding activities b.The
Which statement is not correct regarding the backward pass calculations and its algorithm?
a .The late start timing is passed to the preceding activities
b.The Late finish timing is passed to the preceding activities
c.The late finish timing has to be calculated first.
d. Duration is subtracted from the late finish to calculate the late start