Question: Which statement is NOT true about the project charter? Question 2 6 options: It provides the project manager with the authority to acquire resources. It
Which statement is NOT true about the project charter?
Question options:
It provides the project manager with the authority to acquire resources.
It includes subsidiary plans and baselines.
It formally authorizes the existence of the project.
It includes a highlevel description of the project scope and product requirements
Question point
Which schedule compression method generally incurs additional costs because it involves adding resources?
Question options:
Fast Tracking
Buffering
Laddering
Crashing
Question point
What statement IS true about the Organizational Breakdown Structure?
Question options:
Identifies what specific person will be responsible for each work packagetask in the project.
Describes in high level terms exactly what the project team will deliver to the "client".
Specifies the mapping of tasks to work packages.
Identifies which departments functional units are going to be responsible for or the "owners" of each work package.
Question point
Which statement is TRUE about project phases?
Question options:
Phases must be completed sequentially.
Phases cannot overlap or be conducted concurrently.
Processes from all five process groups may be conducted in each phase.
The planning processes will be conducted only during the planning phase.
Question point
What might be the best way to "manage" a stakeholder who has high interest in your project but no power to interfere?
Question options:
Monitor
Keep informed
Send reports occasionally
Keep satisfied
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock