Question: Which statement is NOT true about the project charter? It includes the stakeholder communication register. It specifies the project's purpose. It provides the project manager
Which statement is NOT true about the project charter?
It includes the stakeholder communication register.
It specifies the project's purpose.
It provides the project manager with the authority to acquire resources.
It formerly authorizes the existence of the project.