Question: Which statement is true about Project Scheduling? A. Slack is defined as the difference between the earliest start and the latest finish of a task.
Which statement is true about Project Scheduling?
A. Slack is defined as the difference between the earliest start and the latest finish of a task.
B. The critical path seldom has a slack time of zero.
C. Project crashing is an effort to maximize project duration.
D. The earliest finish for a task is equal to the early start plus the task duration.
E. None of the above statements are true.