Question: Which statement regarding forward pass analysis is true? A Forward pass analysis determines the end date of the project. B Forward pass analysis is used

Which statement regarding forward pass analysis is true?
A
Forward pass analysis determines the end date of the project.
B
Forward pass analysis is used to determine the shortest possible duration of the schedule.
C
Forward pass analysis is used to determine late start and late finish dates for each activity.
D
Forward pass analysis determines the activity dependencies and number of paths.