Question: Which statements are correct regarding Pegging Analysis and the Build Plan? ( choose 2 ) Use Pegging Analysis to find out how much of next
Which statements are correct regarding Pegging Analysis and the Build Plan? choose
Use Pegging Analysis to find out how much of next month's planned orders are caused by actual sales orders, or just forecast.
The Build Plan has the option to display any combination of items, resources and suppliers that are associated with an assembly
To monitor critical components and bottleneck resources for an important assembly, you need two Build Plans, one for components, one for resources.
The Build Plan is a very flexible tool to display various requirements over time, but is not used for taking action.
Both require major setup effort before they can be useful