Question: Which technique uses historical data from similar projects to estimate activity durations?Select one:A . Three - Point EstimatingB.Gantt ChartsC.Decision MetricsD.PERT Estimation

Which technique uses historical data from similar projects to estimate activity durations?Select one:A.Three-Point EstimatingB.Gantt ChartsC.Decision MetricsD.PERT Estimation