Question: Which tool or technique is commonly used for estimating activity durations in project schedule management? A . Expert judgment B . Variance analysis C .
Which tool or technique is commonly used for estimating activity durations in project schedule management?
A Expert judgment
B Variance analysis
C Monte Carlo simulation
D Control charts