Question: Which type of activity relationship shall be considered when developing the sequencing of activities that need to be performed on a project? Group of answer
Which type of activity relationship shall be considered when developing the sequencing of activities that need to be performed on a project? Group of answer choices A. Preferential relationship B. Resource relationship C. Safety relationship D. Physical relationship E. All the above