Question: Which would not be questions asked by the project audit team of a completed project? a. Did the project conform to plan? b. Have has
Which would not be questions asked by the project audit team of a completed project?
a. Did the project conform to plan?
b. Have has the staff been assigned to new work?
c. Have the costs been allocated correctly?
d. Were the right people and talent assigned to the project?
e. Was senior management's support adequate?
Which of the following statements is correct?
a. A negative CPI suggests the project is over
b. The SPI tells the project manager how many time units the project is behind or ahead of schedule
c. If project crashing is required it suggests the normal time estimates were inaccurate
d. the critical path is the longest path through the project
e. All of the above