Question: Which would not be questions asked by the project audit team of a completed project? a. Did the project conform to plan? b. Have has

Which would not be questions asked by the project audit team of a completed project?

a. Did the project conform to plan?

b. Have has the staff been assigned to new work?

c. Have the costs been allocated correctly?

d. Were the right people and talent assigned to the project?

e. Was senior management's support adequate?

Which of the following statements is correct?

a. A negative CPI suggests the project is over

b. The SPI tells the project manager how many time units the project is behind or ahead of schedule

c. If project crashing is required it suggests the normal time estimates were inaccurate

d. the critical path is the longest path through the project

e. All of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!