Question: = While a project has been ongoing, there has been major changes to its cost and schedule. Given the amounts which follow what what would

= While a project has been ongoing, there has
= While a project has been ongoing, there has been major changes to its cost and schedule. Given the amounts which follow what what would be the EAC? BAC 300,000 AC 100,000 EV 140,000 PV = 130,000 Enter your answer without any units to the nearest whole. = =