Question: While budgeting for a repetitive task in project the team have estimated that the the first cycle of the task will required 1 0 hours

While budgeting for a repetitive task in project the team have estimated that the the first cycle of the task will required 10 hours to complete. Assuming a 70% learning rate, the fifth cycle of the task to 2 decimal places is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer