Question: - While completing work, a project team tells you that a work package has been forgotten in the WBS what is the best thing to
While completing work, a project team tells
you that a work package has been forgotten in the
WBS what is the best thing to do
AWait to a change request to be processed
BInclude it in the WBS
CInclude it only in the net work diagram
DInclude in estimate but not the activity list