Question: While conducting earned value management, the Project Manager of a software development company receives a request from a stakeholder for the most current cost estimate

While conducting earned value management, the Project Manager of a software development company receives a request from a stakeholder for the most current cost estimate report. Specifically, the stakeholder needs to know the value of the work completed against actual cost. Which formula will the Project Manager use to calculate this information?
Question 19Select one:
a.
EV/PV
b.
EV / AC
c.
EV-PV
d.
EV-AC